0381

  • Industry Power
  • Problem Chemical Attack, Concrete Repair, and Floor Protection Systems
  • Country Cyprus
  • Project Goal

    Electricity Authority Cyprus trusted ENECON Mesogios LTD to provide them with the best solution in the market for repair and protect of a concrete secondary chemical containment area by utilizing CHEMCLAD XC.

  • Products Used CHEMCLAD P4C, CHEMCLAD XC, and ENECRETE WS
  • Status Completed

The power plant station of EAC which is located at Dhekelia, was needed ENECON’s solution. The concrete chemical containment area had to be rebuilt and protected with CHEMCLAD XC.

The very corroded concrete bases of the chemical containment tanks were first cleaned from debris and loose material and then they were rebuilt. Afterwards, CHEMCLAD P4C was used as a primer.

As a top coat, CHEMCLAD XC was utilized which is the optimum solution for the protection of the concrete area form the sulphuric acid and caustic soda that the tanks store.

 

Before

Work in Progress

Application of P4C Primer

Application of CHEMCLAD XC